PROCUREMENT AND INSTALLATION OF OVERHAUL ELECTRIC MOTOR PUMPS, TRANSFER PUMPS, CABLES/PIPES AT YOLA AND JIMETA WATER TREATMENT PLANTS, WELDING OF RESERVOIRS AND REPAIR WORKS. THE TWO PLANTS ARE CURRENTLY SUPPLYING 23 MILLION LITRES/DAY AS AGAINST 9MILLION LITRES/DAY TO RESIDENTS OF JIMETA, YOLA AND ENVIRONS (COMPLETED).

 PROCUREMENT AND INSTALLATION OF SUBMERSIBLE PUMPS, CABLES/PIPES AT LUGGERE, GMMC, KAREWA, BEKAJI, DANDU, YELWA AREAS OF J/YOLA, ALSO IN FUFORE AND GUYUK TOWNS (COMPLETED).

REHABILITATION AND UPGRADING OF WATER SUPPLY SCHEMES IN: GULAK, HONG, UBA, MICHIKA, PELLA, GARKIDA, MAIHA, GOMBI AND NUMAN LGAS (COMPLETED).

 REHABILITATION AND UPGRADING OF WATER SUPPLY SCHEMES IN FUFORE AND MUBI LGAS (COMPLETED).

CONSTRUCTED OVER 295 NUMBER OF HAND PUMP BOREHOLES ACROSS THE SEVEN (7) LGAS OF THE STATE AFFECTED BY INSURGENCY, 100% COMPLETION.

CONSTRUCTED OVER 40 SOLAR POWERED BOREHOLES ACROSS THE SEVEN (7) LGAS OF THE STATE AFFECTED BY INSURGENCY, 100% COMPLETION.